DescriptionWe broke ground on Oakton High School in June 2018, starting a four-year renovation/addition project. Construction is scheduled in four different phases, with phase one taking approximately two years. Phase one includes an addition to the front of the building including a new main office, student service office, security office, clinic, library and science wing. Also included in this phase will be a dance room and newly renovated softball complex. Over the summer, work will include renovations and updates to the Main/Auxiliary Gyms, Cafeteria and Weight Rooms.
Highlighted areas of work for the remaining phases will include several additions for Performing Arts, classrooms and the joining the two buildings, creating a courtyard. Renovations will continue on existing classrooms, the theater, main gym, art and CTE classrooms.